Logos + North Wilts Canal Header

 

 

RIVER KEY AQUEDUCT - DIARY OF A WORK PARTY ORGANISER

2001    2002    2003    2004    2005


Dec 2000   Took over the River Key Aqueduct

2001

14/01/01     Burning scrub, clearing site

28/01/01     Burning scrub, brick recovery from wall

04/02/01     Cutting down tree branches across River Key

11/02/01     Cleaning bricks, taking out trees across the top of the aqueduct

21/02/01     Foot & Mouth epidemic started, stopping any further work on the site for a while

10/06/01     Back on aqueduct, working on pump?

12/07/01     Pulled out tree on south end of aqueduct

15/07/01     Removed top stones from aqueduct, cleared vegetation from south wall

22/07/01     Clear loose rocks from north side, finalise vegetation from south side

29/07/01     Remove tree roots, make walk-way

04/08/01     Fencing on bank

19/08/01     Clearing stumps and clearing back end of culvert

13/11/01     Putting in dam at the end of two culverts

24/11/01     Clear ditch, cut back trees, fill rest of sandbags with clay

31/11/01     Level bank on north side, clear out centre in north side of river bed

2002

09/01/02     Finalise dam by adding clay-filled sand bags, move pump to the aqueduct

12/01/02     Try out pump

17/01/02     Make walk way with tree trunks & pallets

18/01/02     View & purchase container for £350 + VAT.  Lorry got stuck in mud trying to deliver it and had to be pulled out by Dave's Discovery              

25/01/02     Built walk way.  Tidy up.

03/02/02     Moving trailer from Morningside to aqueduct

14/03/02     Scaffolding delivered

17/03/02     Fix fencing, clear wood out of river, picked up 16 scaffolding boards & gantry

04/04/02     Alan Tanzel came to help put up scaffolding

07/04/02     Fitted hoist beam etc, tried out hoist & generator

14/04/02     Hoist training, painting container, strip down pump, measure for finger guard

22/04/02     modify scaffolding, fit and drill finger guard

25/04/02     Paint container roof, safety covers on scaffolding, measure for hanging wheelbarrows, set up kitchen                              

28/04/02     New Honda pump trial

05/05/02     Another pump trial - now working, 16 barrows loads taken out

11/05/02     60 barrow loads dug out of centre culvert

12/05/02     86 barrows of silt dug out of centre culvert

23/05/02     62 barrows of silt dug out of centre culvert

01/06/02     Kingdom coach tour party to look around the aqueduct

22/06/02     Scrub bashing

30/06/02     Digging out bricks from culvert

15/07/02     Digging out mud from south end of culvert

21/07/02     Digging out centre collapse in culvert & south end pier, Receive dumper truck

22/07/02     Start work on dumper truck

28/07/02     Bricklaying right hand side of centre pier - south side & beginning of left hand side of centre pier. Lay bricks in layers to repair centre collapse, dug out 61 barrows of silt from centre culvert

04/08/02     Excess rain stopped digging because of water level being too high

15/08/02     Build scaffold platforms for Ron Robertson on south side

18/08/02     Dug 40 barrows out of centre culvert, rebuilding left hand centre culvert pier on south side

25/08/02     Finalise centre culvert roof brickwork, rebuilding south pier

01/09/02     Building south pier, completed digging silt out of centre culvert, started clearing the entrance on east culvert

03/09/02     Move hoist from centre to east culvert

08/09/02     Start clearing east culvert

15/09/02     Clear east culvert, finalise centre arch on south face

22/09/02     Clear 80 barrows of silt from centre of east culvert

29/09/02     Clearing more silt from centre of east culvert, puddle in blue clay to seal centre of mended collapse

06/10/02     Ron completed centre & east culvert face - south side, dug out 105 barrows of silt from east culvert

08/10/02     Fit scaffold over river on south side

13/10/02     Completed silt clearing from east culvert

03/11/02     Cleared top of south wall to expose position of towpath wall

                   General maintainance & clearing up of site carried out when bad weather stopped anything else being done

01/12/02     Help Alan Timpson clear out his garage

08/12/02     First time for 8 weeks the water level is low enough to finalise south arches & pump out water to remove frame and acro jacks, dig out & add shuttering to major collapse, work on towpath wall base, cut steps into bank                          

09/12/02     Complete south arches, remove frame & scaffold in east culvert, finalise shuttering in major collapse

22/12/02     Because of high water, cleared top of south side wall.  Cut branches off trees

2003

05/01/03     Cut trees on south top side wall.  Remove all scaffolding from south side.  Very cold. 

06/01/03     Re-lay boards.  Take off fittings & store scaffolding tubes.

08/01/03     Went to Alan Timpson's to remove engine from dumper to garage.  Can now scrap other dumper.

12/01/03     Worked on south side wall clearing trees

23/01/03     Still clearing stumps from south side wall. 

23/02/03     Build scaffold hoist for south west wall.  Remove gantry from north scaffolding

27/02/03     Work on dumper truck at Alan's

02/03/03     Build and finalise the south road wall hoist gantry (Alan Cowes helped)

09/03/03     Set hoist on scaffolding south road wall and dig out river silt - to fill in centre hole in canal route

18/03/03     Digging out south road wall bank.  Sort thin bricks & clean thick ones.  Remove stump from river

23/03/03     Clean north east arch bricks ready for Ron Robertson next week.  Paint yellow & blue stripes on scaffolding.  Clean wall of ivy & spray with weed killer

30/03/03     Clean arches again.  Pump out water.  Mend Honda pump.  Build towpath foundation wall 2/3rds complete

6/04/03       Build lower arches of west culvert, north side.  Finish building base of towpath wall

13/04/03     Build from base start of centre north arch (saw sill extension for the 1st time).  Build area to receive 4 tons of gravel

27/04/03     Rebuilding north arches

28/04/03     Pick up bricks from Summit lock and transfer to River Key Aqueduct

29/04/03     Bricklaying north face arches

03/05/03     Lower scaffolding to accomodate formers on north arches

04/05/03     Rebuilding arches and centre collapse.  Pick up 250 thin bricks from Summit lock

11/05/03     Ron bricking north arches.  Set 2 off formers east/centre culverts, north side.  Alan doing more brickwork on the centre collapse. 

15/06/03     Still rebuilding north arches & finalising centre collapse

29/06/03     Building last north west arch.  Set up clay bath with water to soften it

06/07/03     Remove large stones & build top of all arches ready to rebuild wall.  Set shuttering for towpath wall for delivery of concrete next Saturday

12/07/03     Concrete delivered for towpath wall foundation.  Fix 2 stringer stones.

20/07/03     3rd row of stones to north wall.  Site scrub bashing, including river bank, ready for WRG.  Bags for grey clay constructed and filled

27/07/03     Scarecrow weekend at Purton Stoke.  Remove top scaffolding.  Raise lower platform to height of stones

03/08/03     WRG  20+ to train for hoist - work as per report.  They were there for a week.

10/08/03     Bricking east culvert

17/08/03     Remove road scaffolding.  Brickwork east culvert

21/08/03     Add centre scaffold pieces to remove silt later.  Bricking centre culvert.  Create entrance for dredging diggers

24/08/03     Bricking up east collapse

25/08/03     Publicity stand at Cricklade Show

19/10/03     Clear centre culvert of silt using hoist

21/10/03     Car came through hedge and ended up on its nose in the river.  Scaffolding damaged

24/10/03     Rented digger to open up centre culvert and to take more out of River Key

26/10/03     Still using digger to open centre culvert.  Remove the rest of the damaged scaffolding.

28/10/03     Digger picked up with £200 damage to doors

02/11/03     Fit fencing.  Bricklaying centre culvert

09/11/03     Heavy rain.  Clean up site.  Check scaffolding

30/11/03     Shore up centre culvert.  Clay wall

07/12/03     Walk to follow the course of the River Key, to check water levels, then 5 onto White Hart for lunch

23/12/03     Cleared culvert of brush wood 

2004

04/01/04     Fixed chestnut fencing to centre culvert opening.  Cleared brushwood

01/02/04     2 trees blown over in high winds from the day before

08/02/04     Added extra layer to top of north wall.  Planted trees in gap in road hedge, caused by the car accident

15/02/04     Working on trailer.  Raised scaffolding level by 3ft

22/02/04     Continue building scaffolding.  Pull down shuttering on centre culvert - scaffold bars and boards bending

29/02/04     Raise height of hoist to working level.  Rebuild shuttering on centre culvert with wood piers.

07/03/04     Set up hoist.  Used once only.  Strengthend  shuttering on centre culvert

28/03/04     Pumped out water.  Removed clay from centre culvert

04/04/04     Clearing mud from centre culvert

17/04/04     Alan & Dave welded trailer and added light board

18/04/04     Finalised clearing of centre culvert

02/05/04     Building north face of wall.  Sorting large bricks.  Cleaning bricks.  Building centre culvert roof.  Fit hand rail

                   The same for the next few weeks while Dave, Alan, Barbara & Liz are in Canada 

06/06/04     Moving formers on centre culvert.  Finish off top of north end wall

13/06/04     Brickwork on centre culvert.  Support Ron

20/06/04     Finnished centre culvert roof.  Finished centre culvert roof.  Started pointing east culvert

                   Road blocked off for new sewage pipe for three weeks

27/06/04     Removed formers from centre culvert.  Pointing east culvert.  Bricking centre culvert.  Ceili & Bess's first visit to aqueduct

04/07/04     Pointing again.  Ron fell in the water

08/08/04     Finished pointing both centre and east culverts.  Cleaning both of wood and planks etc.

22/08/04     16 volunteers!!  North wall scaffolding removed and stored on a rack.  Clean and grease acro jacks.  Strim banks

28/08/04     Temporary fence added to north wall.  Tree removed to aid digger access.  Tent put up on Cricklade show field in howling gale

05/09/04     Clear for digger.  Strim top bank.  Clear shuttering from centre culvert

12/09/04     Cut scaffold tube that was damaged in the car accident.  Walk Hayes Knoll lock and Chaddington lock, because Pam, Paul & Steve had not seen them before.

19/09/04     Start building north west wing wall.  Clean bricks.  Move sand pit for digger

25/09/04     13 ton digger and digger driver from Holland Handling.  Move coffer dam to west (road) culvert.  Fill centre culvert, the roof hole.  Dredge river towards Cricklade

26/09/04     Add fencing to north and south walls.  Pick up stone from Wootton Bassett.  Clear site of glass

03/10/04     Fill 30 sandbags with blue clay to soak in the river inside coffer dam.  Building hoist gantry.  Clear glass from site to protect wildlife and wellies.  Hayes Knoll Lock bought this week.  Clearing scrub.  Have £4,000 grant to use by November 16th.  Chain saw ordered.

10/10/04     Clearing Hayes Knoll lock and putting up scaffolding to south wall of aqueduct

17/10/14     Hayes Knoll lock clearing

22/10/04     Holland Handling, Hilary, Mike & John levelling Hayes Knoll lock for security fencing

23/10/04     Fitting security fencing around perimeter of Hayes Knoll lock

30/10/04     Scrub bashing at Hayes Knoll lock.  Picked up cement mixer from Laura's.  Clean up site taking all rubbish to the dump at Purton

07/11/04     Seal coffer dams.  Clean bricks.  Set up platform for pump

09/11/04     Digger hired for 3 days from Holland Handling clearing a space at Hayes Knoll lock, along the verge, for car parking

14/11/04     Wing walls.  Fill up 24 sandbags with clay for sealing the dam.  Clean bricks

28/11/04     Building north west wing wall.  Exposing north east wing wall.  Pointing south wall. Mend pump.  Clean bricks

05/12/04     Continuing west wing walls adding bricks to top.  Clear foundations for east wing wall to find route

12/12/04     Ron finished north west wing wall.  Clear east wing wall.  Clean bricks

 2005 

20/02/05     Rebuilding north wing wall, east side.  Clearing west culvert.

 

03/05 to      Rebuild east wing wall

Present      Rebuild towpath wall using bricks harvested from Hayes Knoll

                   Fix holes etc. in west culvert

                   Start work at Hayes Knoll lock, clearing site for cabin and survey work

 


Send mail to canalwebmaster@northwiltscanal.org.uk with questions or comments about this web site.
Site developed by Steve Earl.
Last modified: 13/01/2006.